Education · Aarhus, Denmark · 2025

A school campus that teaches with its own power data

310 kWp across four buildings and 16 staff chargers, with live data in class.

N50 m

Site plan

Skovbakke School Trust

Aarhus, Denmark

  • Solar array, 310 kWp
  • 16 charge points
  • Trees and planting kept
Completed
2025
Drawn by
Lumora engineering
System size
310 kWp
Yearly generation
295 MWh
Saved a year
€48,000
Payback
5.9 years
CO₂ avoided a year
115 t

01The challenge

Skovbakke's trust wanted to cut energy costs across its campus and give students something real to study. Its connection was too small for the staff chargers it had promised, and roofs could only be worked on in school holidays.

02What we built

We installed arrays on four buildings over two summer holidays, with chargers in the staff car park managed against the campus connection. A display in the science block shows the live output, and teachers get the raw data for lessons.

03The result

The campus makes 295 MWh a year. The chargers run within the existing connection, and two year groups now use the system's data in maths and physics.

04

How the project ran

1

Assessment

March 2024

Four roofs, the campus connection and the staff travel survey.

2

Design

April to June 2024

Holiday-only build plan, charger layout and the data feed for teachers.

3

Installation

July 2024 and July 2025

Two summer holidays, two buildings each, no work during term.

4

Monitoring

From August 2025

Live display in the science block, with yearly data sent to the trust.

The students check the display before the weather forecast now.
Lise Damgaard, Head of Science, Skovbakke School Trust